Gazette Notice No. 1128 of 2025

NEMA invites public comments within 30 days on the environmental impact study for Muwariziki Sugar Millers Limited's proposed sugar factory in Rangwe Sub-county, Homabay County.

Official PDF · 1.2 MB

Whole issue, from Kenya Law. This notice starts on printed page 288.

AI-extractedAgreement between models, not verified accuracy.

What the notice says

  1. Public comments

    Link

Schedule 9 rows

Anticipated impacts and proposed mitigation measures
Environmental ImpactsMitigation Measures
Occupational health and safety risksProvision of appropriate Personal Protective Equipment. | Safety education and training for workers. | Barricading the construction area appropriately and posting public warnings. | Provision of appropriate onsite sanitary convenience for workers. | Establishing emergency procedures against hazards and | Ensuring the workers stay aware/educated on following them and commensurate to the magnitude and type of emergency, by conducting regular drills and involving the neighboring people. | Display signage warning of potential hazards at various sections of the plant
Air pollutionWatering all active construction areas as and when necessary to lay dust. | Avoid excavation works in extremely dry weathers. | A speed limit of 10km/hr. shall apply to all construction vehicles to limit dust. | Avoid overloading the bagasse for efficient burning. | Planting appropriate trees, shrubs and flowers to compensate for emissions. | Use acceptable emission control technologies. ESPs proposed for stack pollution control. | Conduct routine air quality sampling for analysis to comply with the set standards.
Noise pollutionRestriction of the work hours during the construction phase from 7 a.m. to 6 p.m. during weekdays. | All machinery used during construction shall be maintained in a sound mechanical condition with regular servicing. | Limit pick-up trucks and other small equipment to a minimum idling time and observe a common-sense approach to machine use and encourage workers to shut them off whenever possible. | Procure and provide adequate earplugs to workers at peak noise producing areas. | Regularly service machinery and equipment to ensure that they are in good condition. | Sensitize truck drivers to avoid unnecessary hooting and running of vehicle engines. | Comply with the Noise Regulations, 2009.
Solid waste generationDesignate a waste disposal site for spoil soil and other construction waste. | Segregate waste and recover reusable materials for reuse, recycle. | Use of durable, long-lasting materials that will not need to be replaced as often, thereby reducing the amount of construction waste generated over time. | Construction waste will be recycled or reused to ensure that materials that would otherwise be disposed of as waste are diverted for productive uses. | Provide facilities for proper handling and storage of construction materials to reduce the amount of waste caused by damage or exposure to the elements. | Consider the use of recycled or refurbished construction materials where feasible. | Use of bagasse as fuel in boilers for steam and power production; making mechanical paper, drying of sediments for use as fertilizers.
Increased water demandImmediately drill a borehole to supplement water sourced from River Rangwe. | Quick fixing of licking pipes and toilet cistern. | Reduce water delivery in taps, through the installation of low flow devices or aerators on taps.
Increased traffic flow and road safety concernsConstruction vehicles to enter and leave the site through designated paths only. | Posting traffic warning signs on both approaches to the construction site to warn other road users of traffic risks. | Strict adherence to speed limits near the construction area of 10 km/hr. | Clearly marking parking spaces, installation and maintenance of traffic guide signage.
Waste water generationMonitor the quality of wastewater discharged from the facility. | Vinasse shall be concentrated and utilized in boiler as fuel. | Spent lees shall be treated in CPU and recycled for molasses dilution. | Vinasse evaporator condensate shall be treated in CPU and recycled for molasses dilution. | Cooling tower blow down shall be treated in CPU and recycled for cooling tower make up and pump sealing. | WTP rejects and boiler blow down shall be treated in CPU and recycled for cooling tower make up and washings.
Oil spills/discharge of waste oilConduct regular inspections of tanks, pipelines, valves, and connections to identify any signs of wear, corrosion, or leaks. | Implement a preventive maintenance schedule for all equipment handling molasses to avoid equipment failure that could lead to spills. | Build dyke wall around the molasses tank to contain molasses in case of accidental spillages. | Train employees on the proper handling of molasses, focusing on safety procedures, emergency response, and spill prevention techniques. | Establish clear safety protocols for transferring molasses between tanks, vehicles, and other equipment. | Conduct regular spill response drills to ensure that employees are well-prepared to respond quickly and effectively in the event of a spill. | Use automated control systems that can regulate the flow of molasses, ensuring that overflows are prevented.
Fire hazards and emergenciesDevelop and implement a fire and emergency evacuation plan. | Procure and provide adequate firefighting equipment and place them strategically within the plant. | Ensure firefighting equipment are serviced by accredited fire service providers. | Train employees on the use of fire-fighting equipment. | Designate a fire assembly point and clearly display emergency exits. | Display fire safety and warning signage at appropriate sections of the plant. | Ensure proper handling and storage of flammable materials. | Plant operations should be undertaken by authorized personnel only. | Regular inspection and maintenance of electrical appliances. | Conduct annual fire safety audit and fire drills. | Comply with OSHA, 2007.

Everyone named

Signed byMamo B. Mamo, Director-General, National Environment and Management Authority
Places 4Sango/Rabango Sub-location · Genga Location · West Gem Ward · Rangwe Sub-county
Inspection points 3Principal Secretary, Ministry of Environment, Climate Change and Forestry · Director-General, NEMA · County Director of Environment, Homa Bay County
Issuing authorityNational Environment Management Authority
ProponentMuwariziki Sugar Millers Limited
PlanL.R. No. Gem/Genga/1301
CountyHomabay County
Comment recipientDirector-General, NEMA
Also named 2Ministry of Environment, Climate Change and Forestry · dgnema@nema.go.ke
LawEnvironmental Management and Co-ordination Act

Pages for private people, including the deceased and petitioners, are public, but we ask search engines not to list them.

Corrections 0

Corrected by
No corrigendum in the issues we hold.
Refers to
No other notices.

Cite

Kenya Gazette Notice No. 1128 of 2025, Vol. CXXVII No. 20, 31 January 2025, p. 288.

Permalink funua.com/notices/2025/1128/.

About this data

Source
Official PDF of Vol. CXXVII No. 20, from Kenya Law
Extracted by
AI models
Model audit
An independent model agreed with 98 to 99% of compared values for land and succession notices, 97% overall. Agreement between models, not verified accuracy.
Review flag
None on this notice

Filed under: Planning, 2025 · January 2025 · Vol. CXXVII No. 20