Gazette Notice No. 2110 of 2025

The National Environment Management Authority invites public comments on the County Government of Mombasa’s proposed Mombasa Industrial Park assessment report.

Official PDF · 1.6 MB

Whole issue, from Kenya Law. This notice starts on printed page 584.

AI-extractedAgreement between models, not verified accuracy.

What the notice says

  1. Public comments

    Link
    Issuing authority
    National Environment Management Authority
    Proponent
    County Government of Mombasa
    Plan
    MOMBASA INDUSTRIAL PARK (proposed Industrial Park)
    Place
    Mombasa County, Jomvu Kuu Ward, Jomvu Sub-county, NHIF Building (report inspection location), Community (report inspection location), Nairobi (report inspection locations), Popo Road (report inspection location), Mombasa Road (report inspection location)
    Standards body
    World Bank (World Bank guidelines for noise mitigation), ILO (applicable ILO standards on working hours)
    Office
    Principal Secretary, Ministry of Environment and Forestry (report available for inspection during working hours), Director-General, National Environment Management Authority (report inspection and recipient of oral or written comments), County Director of Environment, Mombasa County (report available for inspection during working hours)
    Body
    Ministry of Environment and Forestry (report inspection location)
    Comments
    30 days, as printed
    Comment period start
    the date of publication of this notice
    Comment submission
    oral or written comments to the Director-General, NEMA
    Report
    Environmental Impact Assessment Study Report
    Project description
    Industrial Park with automotive, Pharmaceuticals and Textiles facilities and high-cost production facilities for imports and exports in Jomvu Kuu Ward, Jomvu Sub-county, Mombasa County
    Inspection hours
    during working hours

Schedule 8 rows

ImpactMitigation Measures
Air pollution• Develop a dust management plan. • Record all dust and air quality complaints, identify cause(s), take appropriate measures. • Undertake monitoring close to dusty activities, noting that this may be daily visual inspections, or passive/active monitoring as parameter. • Undertake inspections to ensure compliance with the dust management plan. • Plan potentially dusty activities so that these are located as far from receptors as feasible. • Avoid run off of mud and water and maintain drains in a clean state. • Remove dusty materials form site as soon as possible if not being re-used. If being re-used, cover or vegetate if possible. • Impose speed limits on haul routes and in construction compounds to reduce dust generation. • Minimize drop heights when loading stockpiles or transferring materials. • Avoid waste or vegetation burning. • Undertake watering to attenuate dust near sensitive receptors.
Noise pollution• Minimize noise according to Kenyan standards and World Bank guidelines. • Control noise and vibration on site. • Work programmes should be provided to local communities (e.g., through the local radio (FM) stations) and strictly followed. • Siting noisy plant and equipment as far away as possible from human settlement, and use of barriers (e.g., site huts, acoustic sheds or partitions) to reduce the level of construction noise at receptors wherever practicable. • Working hours for significant noise generating construction work (including works required to upgrade existing access roads or create new ones), will be daytime only. • For machines with fitted enclosures, doors and door seals will be checked to ensure they are in good working order; also, that the doors close properly against the seals. • Throttle settings will be reduced and equipment and plant turned off, when not being used.
Water and soil pollution• No solid waste, fuels or oils should be discharged into surface water bodies • Vehicles should preferably be parked on paved platforms. • Fuel storages should not leak, and should be periodically monitored, and repaired or replaced when necessary. • Maintain fuel and clean vehicles and equipment at workshops/sites with adequate leakage prevention (e.g., impermeable surface, settlers, and oil separator).
Soil erosion/contamination• Remove and store topsoil in separate piles and reinstate after refilling of dug up areas to enable natural re-vegetation. • The Contractor(s) should present procedures for and ensure implementation of measures to protect soils from any accidental or structural contamination.
Solid waste generation• The Contractor to maintain records of types, quantities, origin, (temporary) storage, transport and elimination/reuse of solid waste, and make these available to the works supervisor upon his request, as proof of proper waste management practices. • Any waste including excess soil should be disposed of at NEMA gazetted sites. • Excavated soils should be reused as much as possible as filling material and should be contained after excavation. • Use licensed recycling companies to externally recycle, recover or dispose of waste.
Impacts on flora and fauna• Zone out working areas to reduce ecological destruction, • Restore disturbed natural sites through environmental rehabilitation; restoring top soils and (re-)introduce genetic species similar to those destroyed in order to re-establish the natural local ecology.
Raw material use• Consider environmental performance of suppliers of raw material in the selection process. • Explore ways of reducing raw material use. • Special emphasis should be made on raw materials that may be reused and/or recycled/recovered.
Occupational health and safety• Contractor will develop a Human Resources Policy, which will outline worker rights to be included in all contracts including restrictions on working hours in line with applicable ILO standards, compensation including consideration of overtime, holidays etc. contractor will require its subcontractors to put in place policies in line with national legislation and applicable international legislation and contractor Code of Conduct and Policies. • Contractor will establish contractual clauses (signed code of conduct) to be embedded in the contracts of the workers and sub-contractors that require adherence to Kenyan law and international standards to be upheld related to worker rights. • Contractor and self-employed contractors will assess the H&S risks related with the tasks to be performed during the construction phase. • Contractor will ensure that training on health and safety measures is provided to all construction workers prior to starting to work on the Project and that supervisors have adequate experience to deliver on their responsibilities. • Contractor will develop and implement a Workers Grievance Mechanism for the Project workforce including workers and subcontractors. • Contractor will establish a procedure for the recording and analysis of incidents and lessons learned such that additional actions can be implemented to avoid or minimize occupational health and safety risks. • Contractor will ensure that facilities and work sites are designed and maintained such that robust barriers are in place to prevent accidents. • Contractor will ensure that its Code of Conduct is followed to regulate the performance and behavior of all workers, including provision for disciplinary action for anti-social behavior and non-compliance with health and safety regulations such as lack of use of PPE. • Contractor will develop a Waste Management Plan for the construction phase with clear guidelines for the safe storage and disposal of hazardous waste and handling of hazardous materials.

Everyone named

Signed byMamo B. Mamo, Director-General, National Environment Management Authority
Places 8Mombasa County · Jomvu Kuu Ward · Jomvu Sub-county · NHIF Building · Community · Nairobi · Popo Road · Mombasa Road
Offices 3Principal Secretary, Ministry of Environment and Forestry · Director-General, National Environment Management Authority · County Director of Environment, Mombasa County
Standards bodies 2World Bank · ILO
Issuing authorityNational Environment Management Authority
ProponentCounty Government of Mombasa
PlanMOMBASA INDUSTRIAL PARK
BodyMinistry of Environment and Forestry
LawEnvironmental Management and Co-ordination Act

Pages for private people, including the deceased and petitioners, are public, but we ask search engines not to list them.

Corrections 0

Corrected by
No corrigendum in the issues we hold.
Refers to
No other notices.

Cite

Kenya Gazette Notice No. 2110 of 2025, Vol. CXXVII No. 36, 21 February 2025, p. 584.

Permalink funua.com/notices/2025/2110/.

About this data

Source
Official PDF of Vol. CXXVII No. 36, from Kenya Law
Extracted by
AI models
Model audit
An independent model agreed with 98 to 99% of compared values for land and succession notices, 97% overall. Agreement between models, not verified accuracy.
Review flag
None on this notice

Filed under: Planning, 2025 · February 2025 · Vol. CXXVII No. 36