What the notice says

  1. Public comments

    Link
    Issuing authority
    National Environment Management Authority, Director-General, National Environment Management Authority (Receives oral or written comments.)
    Proponent
    Kenya Ports Authority
    Place
    Port of Mombasa, Mombasa County, Nairobi (Report inspection locations.)
    Body
    Ministry of Environment, Climate Change and Foresty (Report available for inspection.)
    Inspection office
    Principal Secretary, Ministry of Environment, Climate Change and Foresty, County Director of Environment, Mombasa County
    Comments
    30 days, as printed
    Comment period start
    the date of publication of this notice
    Project
    proposed construction of Berth 19B and associated infrastructure at the Port of Mombasa in Mombasa County
    Report url
    www.nema.go.ke

Schedule 5 rows

ImpactsProposed Mitigation Measures
Seabed disturbance during piling as a result of noise and vibration• Minimize seabed disturbance during foundation piling by restricting the pilling to actual point only. • Acoustically improve the piling process by vibratory pile driving and or drilled foundations. • Intrinsic underwater noise measurements be carried out during piling.
Turbidity and sedimentation• Secure the working site with silt curtains. • Use of less intrusive dredging methods • Ensure no leakage of dredged material during transportation to the dumping site. • Onsite turbidity measurements be carried out during construction period.
Increase in total suspended solids in marine water• Secure marine construction site with silt curtains. • Secure adjacent offshore construction site with silt traps. • Monitor suspended solids in marine water during construction period.
Oil and lubricants spills• Immediately fix all noticeable leaks that can result in oil and lubricant spills. • Promptly collect any spills from all working areas my means of appropriate oil and lubricants absorption materials. • Ensure all equipment and machinery are timely serviced as per manufacturer’s recommendations to avoid leakages. • Activate the oil spill response contingency plan in the event of major spills.
Noise• Equipment to be well maintained and serviced. • Proponent to provide ear protector/ ear plugs/ ear mufflers for ear protection. • Monitor noise levels to ensure they are within the prescribed limit as provided for in the Environmental Management and Co-ordination (Noise and Excessive Vibration) (Control) Regulations, 2009.

Everyone named

Signed byMamo B. Mamo, Director-General, National Environment Management Authority
Places 3Port of Mombasa · Mombasa County · Nairobi
Inspection offices 2Principal Secretary, Ministry of Environment, Climate Change and Foresty · County Director of Environment, Mombasa County
Issuing authorityNational Environment Management Authority
ProponentKenya Ports Authority
BodyMinistry of Environment, Climate Change and Foresty
Law 2Environmental Management and Co-ordination Act · Co-ordination Act

Pages for private people, including the deceased and petitioners, are public, but we ask search engines not to list them.

Corrections 0

Corrected by
No corrigendum in the issues we hold.
Cites
Environmental Management and Co-ordination (Noise and Excessive Vibration) (Control) Regulations, 2009

Cite

Kenya Gazette Notice No. 3576 of 2025, Vol. CXXVII No. 58, 21 March 2025, p. 1274.

Permalink funua.com/notices/2025/3576/.

About this data

Source
Official PDF of Vol. CXXVII No. 58, from Kenya Law
Extracted by
AI models
Model audit
An independent model agreed with 98 to 99% of compared values for land and succession notices, 97% overall. Agreement between models, not verified accuracy.
Review flag
None on this notice

Filed under: Planning, 2025 · March 2025 · Vol. CXXVII No. 58