Gazette Notice No. 4795 of 2025

National Environment Management Authority invites public comments on Kenya Ports Authority’s proposed Mombasa Port Development Project Phase III in Port Reitz Mombasa County.

Official PDF · 1.5 MB

Whole issue, from Kenya Law. This notice starts on printed page 1662.

AI-extractedAgreement between models, not verified accuracy.

What the notice says

  1. Public comments

    Link
    Issuing authority
    National Environment Management Authority
    Proponent
    Kenya Ports Authority
    Place
    Port Reitz, Mombasa County, Mombasa harbor (The proposed terminal and shipping berths are parallel to the turning basin.), NHIF Building (Report inspection address.), Ragati Road (Report inspection address.), Upper Hill (Report inspection address.), Nairobi (Report inspection addresses.), Popo Road (Report inspection address.), Mombasa Road (Report inspection address.)
    Body
    NCA (Excavation methodology generated as required by NCA.), Ministry of Environment, Climate Change and Foresty (Ministry where the report is available for inspection.)
    Inspection office
    Principal Secretary, Ministry of Environment, Climate Change and Foresty (Report available for inspection during working hours.), County Director of Environment, Mombasa County (Report available for inspection during working hours.)
    Comment recipient
    Director-General, National Environment Management Authority (Receives oral or written public comments; report also available for inspection during working hours.)
    Project name
    MOMBASA PORT DEVELOPMENT PROJECT PHASE III
    Project description
    Construction of phase 3 involving the construction of a new berth (No.23) and a container terminal to the west of the existing container terminal and shipping berths parallel to the turning basin of the Mombasa harbor. The terminal will be constructed on reclaimed sand and a new access road will also be constructed to supplement the existing connecting and access road to Port Reitz area including other associated facilities and amenities.
    Gps coordinates
    4˚02’54.4’’S 39˚36’39.6’’E
    Comments
    30 days, as printed
    Comment period start
    the date of publication of this notice
    Comment method
    oral or written comments
    Comment email
    dgnema@nema.go.ke
    Report download
    www.nema.go.ke
    Inspection hours
    during working hours

Schedule 9 rows

The following are the anticipated impacts and proposed mitigation measures:-
ImpactsProposed Mitigation Measures
Soil erosion• Install drainage structures to control flow of storm water. • Ensure and management of excavation activities.
Changes in hydrology/ impended drainage/deep excavations• Proper Installation of drainage structures. • Install cascades to break the impact of water flowing in the drains. • Ensure efficiency of drainage structures through proper design and maintenance. • Provide gratings to the drainage channels. • A geotechnical survey shall be conducted and the recommendations thereof followed. There shall be no blasting during excavation. • A methodology for excavation has been generated as required by NCA.
Air pollution• Water Suppression. • Dust Screen. • Regular maintenance of vehicles. • Inspection certificates to construction vehicles. • Observing speed limits. • Training to KPA and Contractors Environment and Social Safeguards Personnel. • Asphalt plant to acquire emission license from NEMA.
Noise pollution• Install suitable barriers to shield compressors and other small stationary equipment where necessary. • Display signs to indicate construction activities. • Maintain all equipment. • The working hours should be in line with NEMA licensing conditions. • Adhere to provisions of Noise Prevention and Control Rules 2005, Legal Notice no. 24 regarding noise limits at the workplace as well as NEMA Noise Excessive Vibration Pollution Control Regulations, 2000.
Public health, occupational health and safety• WIBA & Insurance for workers. • Training. • Maintenance of Equipment. • Provision of PPE. • Dedicated H&S Department (Min.3 pax). • Prepare Occupational Health and Safety Plan in accordance to OSHA 2007. • Provide a well-trained rescue and first aid team as well as a standby boat to act as an ambulance in the event of accidents in the sea. • Create awareness among the channel users on the presence of the dredger and its activities as well as the required safety precautions • Inform in advance marine users the construction plan. • Installation of buoys along construction boundary.
Road traffic disruption• No overloading of trucks and good driving practices to be practiced. • Suitable junction/access point to be provided. • Use of appropriate & legible signage. • Employment of formal flagmen/ women to ensure the public safety. • Follow the recommendations of the traffic management plan.
Insecurity and social impacts• Provision of security guards, CCTV cameras, security lights and other security apparatus during the entire project cycle. • Construction work timings shall only in line with the NEMA licensing conditions.
Increased Water Usage• An alternative water source shall be provided. The proponent shall drill a borehole at the proposed site. • Management of water usage. Avoid unnecessary wastage.
Increased generation of waste• Adopt waste minimization at source. • Adhering to waste management regulations of 2006.

Everyone named

Signed byMamo B. Mamo, Director-General, National Environment Management Authority
Places 9Port Reitz · Mombasa County · Mombasa harbor · NHIF Building · Ragati Road · Upper Hill · Nairobi · Popo Road · Mombasa Road
Bodies 2NCA · Ministry of Environment, Climate Change and Foresty
Inspection offices 2Principal Secretary, Ministry of Environment, Climate Change and Foresty · County Director of Environment, Mombasa County
Issuing authorityNational Environment Management Authority
ProponentKenya Ports Authority
Comment recipientDirector-General, National Environment Management Authority
LawEnvironmental Management and Co-ordination Act

Pages for private people, including the deceased and petitioners, are public, but we ask search engines not to list them.

Corrections 0

Corrected by
No corrigendum in the issues we hold.
Cites
Legal Notice No. 24 of 2005 (no page yet), NEMA Noise Excessive Vibration Pollution Control Regulations, 2000, OSHA 2007, WIBA, waste management regulations of 2006

Cite

Kenya Gazette Notice No. 4795 of 2025, Vol. CXXVII No. 72, 11 April 2025, p. 1662.

Permalink funua.com/notices/2025/4795/.

About this data

Source
Official PDF of Vol. CXXVII No. 72, from Kenya Law
Extracted by
AI models
Model audit
An independent model agreed with 98 to 99% of compared values for land and succession notices, 97% overall. Agreement between models, not verified accuracy.
Review flag
None on this notice

Filed under: Planning, 2025 · April 2025 · Vol. CXXVII No. 72