NEMA invites public comments within 30 days on KenGen's environmental impact assessment report for drilling 42 geothermal wells in Hell's Gate National Park, Nakuru County.
Official PDF · 1.0 MB
Whole issue, from Kenya Law. This notice starts on printed page 138.
AI-extractedAgreement between models, not verified accuracy.
What the notice says
-
L.R. No. 105419/1
Link- Parcel
- L.R. No. 105419/1
- Issuing authority
- National Environment Management Authority
- Proponent
- Kenya Electricity Generating Company Plc
- Place
- Hell’s Gate National Park, Naivasha Sub-county, Nakuru County
- Comments
- 30 days, as printed
- Reason
- Environmental Impact Assessment Study Report for the proposed drilling of 42 geothermal wells
Schedule 11 rows
| Impacts | Proposed Mitigation Measures |
|---|---|
| Air emission and dust pollution | Regular maintenance and servicing of construction machinery and equipment. • Train and sensitize workers on dust minimization techniques and management of air emissions from vehicles and machinery. • Use of dust/fumes arrestors. • Regular monitoring of H2S along the steam pipelines serving the power plant, cooling towers and in the nearby villages. • Develop and implement a H2S emergency preparedness, prevention and response plan. • Compliance with the provisions of the Environmental Management and Co-ordination (Air Quality) Regulations, 2014. |
| Noise pollution | Install noise barriers to reduce exposure to close sensitive receptors. • Limit operation for specific loud equipment or operations to day-time. • Regular monitoring and measurement of noise levels at the site. • Provide at strategic positions, signage in identified noise hazardous areas. • Develop and implement a Noise Management Plan. • Compliance with the requirements of the Environmental Management and Co-ordination (Noise and Excessive Vibration Pollution) (Control) Regulations, 2009. |
| Surface and sub-surface contamination | Ensure storage of chemicals and fuels in designated areas. • Ensure all chemical and fuel storage sites are banded and with impermeable surface. • Develop and implement a spills prevention and emergency response plan for the site. • Training workers on spills response to minimize the risk of chemical spills. |
| Surface water contamination | Implementation of reinjection system to respective reinjection wells to minimize risk of brine and condensate discharges. • Develop a brine management plan. • Continuous monitoring of chemical composition of brine. • Sludge/precipitates to be stored in banded holding sites. • Regular maintenance of wellheads and geothermal fluid pipelines. |
| Solid and liquid waste generation | Develop and implement a Waste Management Plan. • Ensure all oily water discharges flow through an oil–water separator or a grease trap before discharge. • Ensure adequate sanitation in construction sites, road work areas and workers’ camp. • Ensure Hazardous and toxic waste will be collected by a NEMA licensed hazardous waste transporter and disposed-off in a licensed facility. • Compliance with the provisions of the Environmental Management and Co-ordination (Waste Management) Regulations, 2006 and the Factories and Other Places of Work (Hazardous Substances) Rules, 2007. |
| Impact on flora | Ensure selective clearing of vegetation for future re-growth and regeneration. • Clearly delineate areas for land preparation/other activities in the field to prevent loss of vegetation outside of designated works areas. • Monitor invasive plant species at the project area and uproot unwanted germinating plants. • Rehabilitation and reforestation of disturbed areas neighbouring the plant, and outside the project footprint that will be affected by the construction activities. |
| Impact on fauna | Erect bumps and signage in wildlife crossing areas along the roads leading to the site. • Monitor Incident/accident records and other human-wildlife conflicts for appropriate corrective measures. • Fencing work areas to prevent animal entry and minimize light/disturbance impacts during the night time. • Installation of safety barriers to avoid wildlife contact with hot pipelines, should temperatures exceed safe levels. • Implementation of reinjection system to minimize risk of brine/condensate discharges on Fauna. • Provision of adequately sized concrete lined storage ponds and/or system shut down in case of reinjection failure. • Ensure steam pipes at known animal migration corridors are elevated or buried under the ground surface as appropriate. |
| Occupation health and safety | Provision and enforce use of all ranges of required PPEs for workers and visitors. • Include standard best practice health and safety provisions in the construction work(s) contract; • Install appropriate safety signage for all work sites. • Training workers in the use of the available information (such as International Chemical Safety Cards – ICSC, Materials Safety Data Sheets – MSDS, or equivalent) and safe work practices. • Compliance with the provisions of the Occupational Safety and Health Act, 2007. |
| Impacts on community health | Regular watering of loose surfaces and covering of loose materials to minimize dust. • Avoid offloading and application of loose construction materials during windy hours. • Introduce speed limits on roads and ensure compliance so as to minimize accidents in the busy environment. • Monitor community health in regard to respiratory illness in collaboration with the local health centres for informed preventive care strategies; • Engage community for notification when noisy construction activities are set to take place. |
| HIV/AIDs and Sexually Transmitted Infections (STIs) | Sensitize workers and the local communities on HIV/AIDs and STIs. • Formation of peer groups from among the project staff to ensure continuity in training and awareness raising. • Awareness creation on the risks of contracting or spreading sexually transmitted diseases. |
| Fire outbreak | Develop an implementable fire policy. • Ensure compliance with fire safety rules under the Occupational Safety and Health Act, 2007. • Undertake regular employee’s trainings and fire drills on the operation and maintenance of the power plant and associated infrastructure. • Periodic inspection and maintenance of potential ignition points. • Install high-performance combustible fixed gas detectors along with electro-optical flame detection. |
Everyone named
Pages for private people, including the deceased and petitioners, are public, but we ask search engines not to list them.
Corrections 0
- Corrected by
- No corrigendum in the issues we hold.
- Refers to
- No other notices.
Cite
Kenya Gazette Notice No. 525 of 2025, Vol. CXXVII No. 12, 17 January 2025, p. 138.Permalink funua.com/notices/2025/525/.
About this data
- Source
- Official PDF of Vol. CXXVII No. 12, from Kenya Law
- Extracted by
- AI models
- Model audit
- An independent model agreed with 98 to 99% of compared values for land and succession notices, 97% overall. Agreement between models, not verified accuracy.
- Review flag
- None on this notice