PlanningGazette notice
Gazette Notice No. 6435 of 2025
The National Environment Management Authority invites public comments on Rever Aviv Limited’s proposed apartment development at Lower Kabete, Kiambu County.
Official PDF · 1.7 MB
Whole issue, from Kenya Law. This notice starts on printed page 2175.
AI-extractedAgreement between models, not verified accuracy.
Items 2
-
L.R NO.KABETE/KIBICHIKO/4742
Link- Parcel
- L.R NO.KABETE/KIBICHIKO/4742
- Issuing authority
- National Environment Management Authority (Received the Environmental Impact Assessment Study Report.)
- Proponent
- Rever Aviv Limited
- Place
- Lower Kabete, Kiambu County, NHIF Building (Report inspection location), Upper Hill (Report inspection address), Nairobi (Report inspection addresses)
- Report inspection office
- Principal Secretary, Ministry of Environment, Climate Change and Foresty (The full report is available for inspection during working hours.), Director General, NEMA (The full report is available for inspection during working hours.), County Director of Environment, Kiambu County (The full report is available for inspection during working hours.)
- Body
- Ministry of Environment, Climate Change and Foresty (Report inspection location)
- Project description
- an ten storey (lower ground, ground plus 10 No. floors) residential building comprising a total of 200 units (7No. 1ofts, 49No. studio Units, 90 one bedroom units, 54 two-bedroom units) management office, ICT room, parking, driveways, children play area, swimming pool, associated facilities and amenities
- Report download
- www.nema.go.ke
-
Public comments 2
Link- Body
- National Environmental Management Authority
- Issuing authority
- Director-General, National Environment Management Authority (Receives oral or written comments to assist the Authority in the decision making process for this project.)
- Comments
- 30 days, as printed
- Comment period start
- the date of publication of this notice
Schedule 15 rows
| Impacts | Mitigation Measures |
|---|---|
| Solid waste generation | • Use of an Integrated Solid Waste Management System; through a hierarchy of options: source reduction, recycling, composting and reuse. • Engage the services of registered waste handlers to collect and transport waste to designated disposal sites and to manage waste in line with the Waste Management Regulations, 2006. |
| Increase generation of waste water | • Connecting and channeling all liquid/effluent wastes to the existing sewer system. • Provision of adequate and appropriate sanitary facilities for the workers during construction phase and tenants during the operation phase of the facility. |
| Exploitation of construction materials | • The Proponent will source building materials such as sand, ballast and hard core from registered quarry and sand mining firms, whose extraction sites have undergone satisfactory environmental impact assessment/audit and received NEMA approval. • b) The Proponent shall consider reuse of building materials and use of recycled building materials where applicable. |
| Increased traffic | • Ensure all construction vehicles to and from the construction site use the designated Entry/Exit to the project site and Ensure there is a traffic marshal at the site directing traffic. • All transportation of construction raw materials and excavated materials are to be conducted at traffic off peak hours only. |
| Soil erosion | • Avoid unnecessary excavations and other soil disturbances that can predispose it to the agents of erosion and Control excavation works especially during rainy / wet conditions. • The stockpiling of construction materials shall be properly controlled and managed. |
| Air pollution/ dust emission | • Regular sprinkling of water on work areas to prevent fugitive dust violations. • Use of dust nets/screens around the construction site to contain and arrest dust. • Provide PPEs to the workers in dusty areas on the site. • Monitor the air pollution levels regularly as per the Air Quality regulations. |
| Noise and excessive vibrations | • Construction works shall be carried out only during the day from 0800hrs to 1700 hrs. • Noise shields shall be used on noisy equipment. • Bill board shall be erected at the construction site entrance to notify of the construction activities and timings. • Regular monitoring of noise levels at the site as per the regulations. |
| Increased water demand | • Provision of adequate underground and roof tanks for water storage • Use water efficient appliances and fixtures for conservation of water. • Prompt detect and repair of all the water fixtures and fittings to reduce water wastage. |
| Increased energy demand | • Use of solar energy as an alternative source of energy. • Monitor energy use during construction and set reasonable limit. • Install and routine maintenance of energy efficient appliances. |
| Surface run-off and storm water management | • Semi permeable materials will be used for construction of pavements. • After completion of construction, the proponent shall embark on comprehensive landscaping. • Drainage channels shall be covered. |
| Disturbance of the existing vegetation | • Preserve the existing natural vegetation as much as possible • Set out a plan for re-vegetation of disturbed areas |
| Risk of fire outbreak | • Provide adequate firefighting equipment and train staff on the use and ensure regular maintenance. • Conduct regular firefighting drills within the site. • Develop and post at the site fire emergency and evacuation procedures. • Maintain on site telephone contacts for fire brigade and ambulance service provider. |
| Oil leakages and spills on the environment | • All machinery shall be keenly inspected not to leak oils on the ground. • Install oil trapping equipment in areas where there is a likelihood of oil spillage. • Proper disposal of waste oil. |
| Emergence and spread of social vices | • The contractor shall install 24hr operating CCTV surveillance which will be monitored regularly. • Offer awareness, guidance and counselling on HIV/AIDS and other STDs to employees. • Ensure enforcement of relevant legal policy on sexual harassment. |
| Occupational health and safety | • All workers shall use properly fitting PPEs to avoid injuries and illness which include working boots, overalls, helmets, goggles, earmuffs, masks, gloves etc. • The contractor shall adapt a suitable emergence response plan to manage occurrence of anticipated hazards during construction phase. • Comply with OSHA, 2007 and all other relevant regulations governing health and safety of workplaces. |
Everyone named
Pages for private people, including the deceased and petitioners, are public, but we ask search engines not to list them.
Corrections 0
- Corrected by
- No corrigendum in the issues we hold.
- Cites
- Waste Management Regulations, 2006, Air Quality regulations, OSHA, 2007
Cite
Kenya Gazette Notice No. 6435 of 2025, Vol. CXXVII No. 93, 16 May 2025, p. 2175.Permalink funua.com/notices/2025/6435/.
About this data
- Source
- Official PDF of Vol. CXXVII No. 93, from Kenya Law
- Extracted by
- AI models
- Model audit
- An independent model agreed with 98 to 99% of compared values for land and succession notices, 97% overall. Agreement between models, not verified accuracy.
- Review flag
- None on this notice
Filed under: Planning, 2025 · May 2025 · Vol. CXXVII No. 93