Gazette Notice No. 8913 of 2025

The National Environment Management Authority invites public comments on Ranam Investment Limited’s proposed residential apartments on L.R. No. 209/13301.

Official PDF · 1.2 MB

Whole issue, from Kenya Law. This notice starts on printed page 4108.

AI-extractedAgreement between models, not verified accuracy.

What the notice says

  1. L.R. NO. 209/13301

    Link
    Parcel
    L.R. NO. 209/13301
    Issuing authority
    National Environmental Management Authority
    Proponent
    Ranam Investment Limited
    Place
    Likoni Lane, Kileleshwa Ward, Nairobi County, Nairobi City County, NHIF Building (Report inspection location), Ragati Road (Report inspection address), Upper Hill (Report inspection address), Nairobi (Report inspection addresses), Popo Road (Report inspection address), Mombasa Road (Report inspection address)
    Body
    Ministry of Environment Climate Change and Foresty (Report available for inspection at the Principal Secretary's office)
    Inspection office
    Principal Secretary, Ministry of Environment Climate Change and Foresty, County Director of Environment, Nairobi City County
    Comment recipient
    Director General, NEMA (Report also available for inspection)
    Project
    proposed residential apartments on plot L.r. No. 209/13301 along Likoni Lane, Kileleshwa Ward, Nairobi County
    Project description
    16 storey (1 No. basement, ground floor, upper ground floor, 14 No. floors plus rooftop floor) residential building consisting a total of 193 residential units (56 one-bedroom units, 83 two-bedroom units and 54 three-bedroom units with DSQ) 247 parking lots, swimming pool, gym, lounge area and other associated facilities and amenities
    Comments
    30 days, as printed
    Comment period start
    date of publication of this notice
    Comment format
    oral or written comments
    Comment purpose
    to assist the Authority in the decision making process for this project
    Report website
    www.nema.go.ke
    Inspection hours
    during working hours

Schedule 7 rows

The following are the anticipated impacts and proposed mitigation measures:
ImpactsMitigation Measures
Noise and vibrations generation• Apply for a License from NEMA whereby maximum permissible noise levels are to be exceeded. • Prescribe appropriate noise reduction measures e.g. restricted working hours and transport hours and noise buffering. • Install portable barriers to shield compressors and other small stationary equipment where necessary and locate stationary noise sources as far from existing sensitive receptors as possible. • Use quiet equipment (i.e. equipment designed with noise control elements such as mufflers). • Ensure use of well serviced vehicles and equipment. • Limit trucks and other small equipment to minimize idling time and switch off idle engines whenever possible.
Air pollution (dust and exhaust emissions)• Provide 2.4-meter-high hoarding along site boundary. • Provide effective dust screen, sheeting or netting where a scaffolding is erected around the perimeter of the building under construction, from the ground floor level of the building up to the highest level of the scaffolding. • Water all active construction areas when necessary. • Cover all trucks hauling soil, sand and other loose materials or require all trucks to maintain at least two feet of freeboard. • Down wash of trucks tyres prior to departure from site. • Vehicle idling time shall be minimized
Waste generation• Use of durable, long-lasting materials that will not need to be replaced as often, thereby reducing the amount of construction waste generated over time. • provide facilities for proper handling and storage of construction materials to reduce the amount of waste caused by damage or exposure to the elements. • Use of building materials that have minimal packaging to avoid the generation of excessive packaging waste. • Use of construction materials containing recycled content when possible and in accordance with accepted standards; and • Adequate collection and storage of waste on site and safe transportation to licensed disposal sites and disposal methods at designated area shall be provided.
Health and safety risks/hazards• Enhance security by ensuring guards are posted around the project site and the strategic placement of security lights around the site. • A roster of all construction workers shall be kept. • Unattended public access to the construction site shall be restricted and only one entry/exit point shall be used • Appropriate health and safety measures shall be implemented. • Warnings and signs should be placed in appropriate places. • Ensure safety education/training of the construction workers. • Appropriate Personal Protective Equipment shall be worn at all times by all within the construction site including visitors. • Install proper fire management equipment and emergency response systems/strategies.
Increased water demand• Promote awareness on water conservation. • Install water meters where applicable. • Determine the monthly water consumption and its cost. • Identify activities and areas that cause high consumption. • Install water-saving devices in the appropriate places (flow regulators, water flow sensors, self-closing taps, low-flush toilets, etc.) • Regularly maintain plumbing fixtures and piping in order to avoid losses. • Replace defective seals and repair damage to water pipes.
Increased energy demand• Identify and use areas/equipment/systems having minimum energy consumption. • Install energy efficient lighting in common areas such as staircases and driveways. • Use alternative energy e.g. solar power for water heating.
Traffic and obstruction along access road• Ensure that the Entry/Exit to the project site is located where it will cause minimal traffic along adjacent roads. • Ensure all construction vehicles to and from the construction site use the designated Entry/Exit to the project site • All transportation of construction raw materials and excavated materials are to be conducted at traffic off peak hours only. • Sensitize truck drivers to avoid unnecessary road obstruction. • Cover all trucks hauling soil, sand and other loose materials to avoid spillage and dust emissions that may interfere with smooth motoring Other mitigation measures are outlined within the report.

Everyone named

Signed byMAMO B, MAMO, Director-General
Places 10Likoni Lane · Kileleshwa Ward · Nairobi County · Nairobi City County · NHIF Building · Ragati Road · Upper Hill · Nairobi · Popo Road · Mombasa Road
Inspection offices 2Principal Secretary, Ministry of Environment Climate Change and Foresty · County Director of Environment, Nairobi City County
Issuing authorityNational Environmental Management Authority
ProponentRanam Investment Limited
ParcelL.R. NO. 209/13301
BodyMinistry of Environment Climate Change and Foresty
Comment recipientDirector General, NEMA
LawEnvironmental Management and Co-ordination Act

Pages for private people, including the deceased and petitioners, are public, but we ask search engines not to list them.

Corrections 0

Corrected by
No corrigendum in the issues we hold.
Refers to
No other notices.

Cite

Kenya Gazette Notice No. 8913 of 2025, Vol. CXXVII No. 145, 4 July 2025, p. 4108.

Permalink funua.com/notices/2025/8913/.

About this data

Source
Official PDF of Vol. CXXVII No. 145, from Kenya Law
Extracted by
AI models
Model audit
An independent model agreed with 98 to 99% of compared values for land and succession notices, 97% overall. Agreement between models, not verified accuracy.
Review flag
None on this notice

Filed under: Planning, 2025 · July 2025 · Vol. CXXVII No. 145